Excavation and fill calculator

Free excavation and fill calculator: rectangular or sloped pit volume, swell/bulking, compacted-fill loose material and truck trips. No sign-up.

Calculation type

Excavation geometry

Vertical sides: L × W × average depth.

Excavation sizes
Swell and truck

Soil shortcut

Shortcuts are starting points—edit if you have measured data.

How are excavation and fill volumes calculated?

Earthworks use three volumes: in-situ (bank) cut, bulked loose haulage volume, and compacted fill. Treating them as equal breaks truck and material plans. This tool uses rectangular or frustum geometry, then applies swell/shrink and truck fill ratio.

Steps

  1. Choose excavation or fill.
  2. Pick rectangular or sloped (bottom–top) geometry.
  3. Enter length, width, depth/thickness and any deducted volume.
  4. Set soil shortcut or your own swell/shrink percentage.
  5. Read truck trips from nominal capacity × fill ratio.

Formulas

Rectangular volume = L × W × D. Sloped frustum = D/3 × (A1 + A2 + √(A1×A2)). Net bank = gross − deduct. Loose haul = net × (1 + swell%/100). Loose fill needed = compacted ÷ (1 − shrink%/100). Trips = ceil(volume ÷ (capacity × fill%)).

Guidance swell ranges

There is no single correct percentage—use lab/spec data when available:

SoilSwell (approx.)Note
Sand10–15%Easy dig, lower swell
Gravel5–15%Granular
Clay20–40%Depends on moisture/PI
Mixed fill20–30%Default shortcut ≈ 25%
Rock / blasted50–80%Measure on site

Worked examples

Use these to verify the tool; replace with your dimensions.

  • 10 × 8 × 2 m cut, 25% swell, 20 m³ truck × 90% fill → 160 m³ bank, 200 m³ loose, 12 trips (~16 m³ spare on last trip).
  • Same plan, 0.50 m compacted fill, 20% shrink loss → 40 m³ compacted, 50 m³ loose, 3 trips.
  • Bottom 10×6, top 12×8, depth 2.5 m, qty 2, 20% swell → ≈386.5 m³ bank, ≈463.8 m³ loose.

Practical tips

  • Trips are volume-based; legal axle weight may force smaller loads.
  • Slope angle/shoring are not designed here—take top sizes from geotech.
  • Do not reuse the same % for swell and shrink.
  • Use deducted volume for existing voids or prior excavation.

Application note

Planning estimate only. Not a substitute for soil investigation, slope/shoring design or contract measurement.

Related calculators

For fill tonnage or overall building cost:

Frequently asked questions

How do I calculate excavation volume?

Multiply L × W × average depth (or use the frustum formula for sloped pits). Apply swell for haul volume and divide by effective truck capacity for trips.

What is bulking / swell?

Soil gains volume when excavated. Loose = bank × (1 + swell%/100). Clay usually swells more than sand.

How are truck trips calculated?

ceil(haul m³ ÷ (nominal m³ × fill ratio)). Check legal weight separately.

How much loose material for fill?

loose = compacted ÷ (1 − shrink%). Example: 40 m³ target at 20% loss → 50 m³ loose.

Rectangular vs sloped mode?

Rectangular assumes vertical sides. Sloped mode uses different top/bottom plan areas via the frustum formula.

Does this design slopes or shoring?

No—only geometric volume and haul/fill planning.